The boat's year
Every boat lives by a yearly cycle, and the skipper who plans by it spends less and sails more. The cycle depends on where the boat is, not on the calendar at home: October is lay-up in the Mediterranean, launch time in New Zealand and the last month of the hurricane season in the Caribbean. Owners who fight the cycle pay rush prices, wait for yards and sail a boat that was finished in a hurry.
The six phases, and what each is for
- End of season: the most important month of the year for the boat. Write the job list while the faults are fresh, book haul-out and winter storage, ask for quotes, order parts with long lead times (sails, , engine parts, electronics).
- Lay-up: the boat ashore or tucked in. The big jobs go here, because yards have time, technicians can give your boat days rather than hours, and you can be there to see the work.
- Pre-season yard work: , engine service, the rig check, the last touches. Yards are at their busiest; anything not booked by now waits.
- Launch: back in the water, a leak check in the slings, a , then short sails close to home before anything long.
- Season: sailing. Small repairs as they come; everything else goes on the list for the end of season. A boat used regularly stays healthier than one that waits.
- Storm or monsoon season in the tropics: the boat ashore with tie-downs, in a recognised storm hole, or out of the belt. This is the tropical lay-up, and the time for the refit.
Two calendars: the boat's and the yard's
Your boat's calendar and the yard's calendar are the same calendar, shared with every other boat in the area. That is why the same job costs more and takes longer in the spring rush. The skipper's rhythm that works everywhere: decide in the autumn, work in the winter, finish in early spring, launch before the crowd. In the tropics, read "autumn" as the end of the sailing season and "winter" as the storm or monsoon months.
The jobs on a cycle longer than a year
Some jobs come round every few years, and they are the ones that surprise owners. Keep a simple table of when each was last done and plan them into the quiet months:
- Every season: engine service, , anodes, antifouling (or every second season with a hard paint), safety gear dates, the rig walk-round, the service when due.
- Every few years: the exhaust elbow, the heat exchanger cleaned, the cutless bearing, hoses and clamps, the sail-drive diaphragm (makers usually say about every seven years), the windlass serviced, the batteries.
- About every ten to fifteen years: standing rigging, many sails, the electronics, the cushions and the canvas.
A cruising boat keeps the same rhythm, on the move
On a long voyage the cycle moves with you: the Caribbean season, the Pacific season, the cyclone season in New Zealand or Australia, the Indian Ocean in the southern winter. Each storm season is the lay-up and the refit; each ocean passage has its window. Plan it with the world voyage planner, and look up each crossing on the ocean passages pages.
How to winterize a boat: the lay-up
When to lay up depends on where the boat is
In the Mediterranean, Europe and North America the boat comes out from about October to April. In Australia, New Zealand and South Africa the winter is six months later, from about May to September. In the tropics there is no winter: boats are laid up through the hurricane or cyclone season, or the monsoon, and the enemies are sun, damp and wind instead of frost. See sailing seasons around the world for your area's months, and book haul-out early: yards fill at the end of every season.
Seasonal timing
- Northern temperate waters
- October to January: end of season and lay-up. February and March: yard work. April and May: launch. June to September: the season (the Mediterranean, Europe, North America, Japan).
- Southern temperate waters
- Everything six months later: April to July end of season and lay-up, August and September yard work, October and November launch, December to March the season (Australia, New Zealand, South Africa, Patagonia).
- The tropics
- No winter, but storms or monsoon: in the Caribbean the season is December to May and the hurricane months June to November; in the South Pacific and northern Australia the season is May to October and the cyclone months November to April; in Thailand the season is November to April and the monsoon May to October.
Tips from experience
- Keep a running job list on the boat (a notebook by the chart table, or the to-do list in your Boat Almanac account) and add to it the moment something annoys you.
- Photograph every fault when you find it; you will not remember which hose it was in February.
- Book haul-out for the date you want, not the date that is left: the good dates go first.
- Order long-lead parts in the autumn: sails, rigging and some engine parts take weeks or months.
- Do one big job a winter, not five half-jobs.
- Use the boat in the shoulder months: the weather is often fine, the marinas are empty and you find the faults before the season.
- On the last sail of the year, write down what you want to be different next year.
What it usually costs depends on
- Where the boat is (berth, yard and labour rates vary greatly between countries and even between nearby harbours).
- When you book (rush-season prices and availability against quiet-season ones).
- How well the cycle was kept before you (deferred work comes back larger).
Ask for written quotes locally: prices differ a great deal between countries, harbours and seasons.
Common mistakes, and the lesson from each
- ❌ Booking the yard in spring. Every boat in the area wants the same slot. Book haul-out and the big jobs in the autumn.
- ❌ Leaving the job list until the new season. By then you have forgotten half of it. Write it on the last sail of the year.
- ❌ Using a northern calendar in the southern hemisphere or the tropics. Plan by your sea area's own year: storms and monsoons decide it, not the date.
- ❌ Launching on the first warm weekend. A launch needs a full day and calm weather: leaks, engine, a short sea trial.
- ❌ Doing everything every year, or nothing. Keep a table of when each job was last done; do what is due, plan what is coming.
- ❌ Ordering parts in the spring. Lead times are longest when everyone orders. Order in the autumn.
- ❌ Leaving the boat unused for most of the season. An idle boat deteriorates faster than a used one: seals dry, fuel ages, damp spreads.
- ❌ Starting the season with the first long passage. Shake the boat down close to home; things break in the first sails.
Go deeper
- Sailing seasons around the world
- Season calendar, month by month
- Annual maintenance calendar
- Winter maintenance
- World voyage planner
← The Skipper's Handbook · ‹ Waste and the environment · Haul-out and the boatyard ›
General guidance from experience, not instructions for your boat: follow the maker's manuals and ask a qualified professional for work you are not sure of.